This article outlines the key aspects of the Flemish PV obligation for large electricity consumers. The article is structured into seven main sections: 1) Regulatory Framework, 2) Scope and Thresholds, 3) Compliance Deadlines and Capacity Requirements, 4) Implementation Options, 5) Exceptions and Deferrals, 6) Enforcement Mechanisms, and 7) Strategic Implementation Guidelines.
The PV obligation forms an essential part of Flanders' broader energy transition strategy. Its primary aim is to stimulate local renewable energy production and enhance the region's energy independence. This obligation stems from the Decree of the Flemish Government containing general provisions on energy policy, commonly known as "the Energy Decree of 19 November 2010". The most recent amendments, such as those introduced by the Decree of the Flemish Government of 17 February 2023 (Article 3, effective: 24 June 2023), have further refined and detailed the specific provisions for this PV obligation. The regulation specifically targets large electricity consumers, intending to leverage their significant consumption profiles and available infrastructure for the large-scale implementation of renewable energy.
Entities and Obligated Parties Involved
The mandate applies to buildings with annual electricity consumption exceeding 1 GWh from 2021 onward. Responsibility lies with the owner, long leaseholder (erfpachter), or building right holder (opstalhouder). For properties with multiple such parties, all are jointly and severally liable for compliance.
Consumption Threshold
The obligation applies when annual electricity consumption exceeds 1 GWh (1,000 MWh) per calendar year, with 2021 as the initial reference year[1].
Exemptions from the Obligation
Buildings are exempt if their average electricity consumption over the three preceding calendar years is more than 10% below the 1 GWh threshold. However, this exemption is invalidated if there was zero electricity consumption in any of those three years, preventing temporary shutdowns from qualifying for exemption.
The exemption clause, based on a consumption reduction of more than 10% below 1 GWh, with the exclusion for zero consumption, indicates that the regulation targets genuinely large, continuous consumers. This implies that companies may consider strategic energy management to bring their consumption below the threshold and potentially avoid the obligation. However, such a reduction must be sustainable and not relate to a temporary dip or closure of a location. Companies should meticulously monitor their annual electricity consumption. A sustained reduction in energy demand, for example, through energy efficiency measures, could lead to an exemption. This, however, requires careful long-term planning and verification to ensure consistent compliance with the exemption conditions.
Installation Deadlines
The Flemish PV obligation has specific deadlines for the commissioning of photovoltaic solar panels:
Progressive Capacity Requirements
The regulation establishes a three-phase increase in minimum required capacity. Each phase requires full compliance with the higher requirements by the specified date.
The minimum peak power requirements are as follows:
ACTION TIP: Don't plan for minimum compliance. The stepped increase from 12.5 to 25 Wp/m² requires a long-term investment strategy. Consider immediate installation at higher capacity or design systems with expansion capability. Integrate these requirements into your capital expenditure planning for 2026-2035.
Determining Required Capacity
Base calculation: Horizontal roof area × required Wp/m² (12.5, 18.75, or 25 Wp/m²)
However, the calculated peak power is subject to the following two caps:
The explicit inclusion of a cap based on the "maximum remaining connectable injection capacity" and the requirement for an "up-to-date grid study" reveal a crucial practical limitation: the capacity of the electricity grid to absorb injected renewable energy. This is not merely a theoretical calculation but a real bottleneck that can significantly affect the feasibility and scale of PV installations. The divisor of 0.7 implies a safety margin or efficiency factor applied by the regulator. Businesses must initiate grid studies early in their planning process. Grid capacity limitations can reduce the required PV installation size, but can also entail significant delays and costs if grid upgrades are necessary. This underscores the need for early engagement with Distribution System Operators.
The Flemish PV obligation offers significant flexibility in how it can be met, with options for direct installation of PV systems, the deployment of alternative renewable energy technologies, or participation in projects.
Option 1: Direct Installation of PV Systems
PV panels can be installed in various locations:
Eligible installation sites include:
An important nuance for installations on another own site or a site of an affiliated company is that only PV panels commissioned after 1 January 2023 are eligible to count towards the obligation.
This is a strategic opportunity for large companies as they can leverage the flexibility in installation locations to optimize their compliance strategy.
Option 2: Alternative Renewable Technologies
As an alternative to PV, other renewable technologies commissioned after January 1, 2023, can satisfy the obligation if installed at the same off-take point or an eligible site in Flanders.
Qualifying alternative technologies:
The deadlines for these alternative technologies are the same as the deadlines for the commissioning of PV panels. For the tightening pathway (2030, 2035), specific later deadlines apply if the initial PV deadline falls before these dates.
Equivalence calculation for alternative technologies:
The Flemish Government will evaluate these alternative renewable energy technologies by 30 June 2025 at the latest.
Companies shall therefore conduct a comprehensive energy audit to determine if alternative technologies better suit their energy profile. They should also consider existing heat demands, available resources (wind conditions, biomass availability), and technical feasibility before selecting an alternative to PV.
Option 3: Participation in External Renewable Projects
Organizations can fulfill the obligation by financially participating in new renewable energy projects in Flanders, either directly or through affiliated companies. The eligible projects are similar to the direct installation options, including PV (various locations), floating PV, overarching PV in agricultural areas, new wind turbines (or repowering), new biomass/biogas CHP, new heat pumps, PV-thermal, and concentrated solar thermal installations.
The participation agreement must be entered into by the deadline for commissioning photovoltaic solar panels, with specific later deadlines for the tightening pathway (2030, 2035). The projects must be located in the Flemish Region.
For PV projects, the required participation must be for at least the peak power that meets the requirements explained above. For other technologies, the participation must include at least a nominal capacity that generates an amount of electricity equivalent to the electricity production that would result from fulfilling the PV obligation.
Financial participation requirements:
The new installation in which participation occurs must have been commissioned from 1 January 2023 and by the PV commissioning deadline at the latest. Specific later commissioning dates apply to projects that meet the tightening pathway. Peak power or nominal capacity of project installations placed to fulfil other obligations under this decree are not eligible to count towards this PV obligation.
Required participation agreement details for VEKA submission:
Project implementers must submit a comprehensive participant list with associated data to VEKA for each project.
The regulation provides mechanisms for temporary deferral or permanent exceptions under specific circumstances:
Temporary Deferral for Construction Works
Owners, building right holders, or long leaseholders can apply to VEKA for a deferral for buildings that will be fully or partially demolished and reconstructed, or whose roof will be fully or partially replaced. The application must demonstrate that one or more of these circumstances apply. VEKA must inform the applicant of its decision regarding the deferral request within sixty days of receiving the application. If granted, the deferral period is five years from the notification of the decision. Within this deferral period, specific requirements apply for submitting proof:
An appeal to an administrative court regarding the planning permission for demolition suspends the aforementioned deadlines.
Permanent Exception for Building Demolition
In the event of a full or partial demolition of a building without reconstruction, the PV obligation does not apply to the portion of the roof area that is not reconstructed. The obligated party must notify VEKA of the demolition without reconstruction in such a case. As proof of demolition without reconstruction, the owner, long leaseholder, or building right holder must submit planning permission for urban development acts for the demolition to VEKA by three years after the planned demolition was reported to VEKA, provided a demolition permit is required.
The exception ceases to apply if:
An appeal to an administrative court regarding the planning permission for demolition suspends the aforementioned deadlines.
Role and Authority of VEKA
The Flemish Energy and Climate Agency (VEKA) is the designated authority for supervising and controlling compliance with the PV obligation. VEKA is authorised to request horizontal roof area data and other necessary information from owners, long leaseholders, building right holders of buildings, or from electricity consumers of those buildings. This data must be provided within sixty days of receiving the request. Furthermore, VEKA is the data controller for personal data processed under this regulation.
Penalties for Non-Compliance
VEKA imposes a fine of €400 per kilowatt-peak below the required capacity for installations not operational by the applicable deadline.
Important: These fines are non-absolutory - paying them does not eliminate the obligation. If non-compliance continues, additional fines can be imposed until full compliance is achieved. Accordingly, a non-compliance is not financially viable. The €400/kWp fine, combined with the persistent obligation, creates cumulative penalties that quickly exceed installation costs. For a 500 kWp shortfall, the initial fine alone would be €200,000, with potential for repeated penalties until compliance.
Early Planning and Strategy Development
Given the complex interplay of deadlines, capacity calculations, alternative pathways, and potential grid limitations, a proactive and holistic approach is essential. Businesses should conduct a thorough evaluation of their electricity consumption patterns, available horizontal roof area, structural integrity of buildings, and the potential for alternative technologies.
Financing and Operational Models
The regulation explicitly allows the obligation to be met through direct installation or participation in projects, offering flexibility in ownership and operational models. Businesses may consider Power Purchase Agreements (PPAs) with external PV developers or participate in joint ventures for renewable energy projects.
Technical and Legal Requirements
It is crucial to understand the precise definitions (e.g., horizontal roof area, affiliated company), deadlines, and the nuances of the equivalence calculations. The joint and several liability for multiple owners necessitates clear internal agreements. Technically, accurate measurements of horizontal roof area, assessment of structural capacity, detailed grid studies, and feasibility studies for alternative technologies are of paramount importance.
This report has provided a detailed examination of the Flemish PV obligation for large electricity consumers, outlining its scope, deadlines, capacity requirements, and various compliance pathways. The regulation is robust, with clear enforcement mechanisms and significant financial penalties for non-compliance, underscoring the importance of timely and accurate action.
While challenging, the Flemish PV obligation offers flexibility through multiple compliance pathways. Act now to assess your specific situation, develop a tailored strategy, and implement a cost-effective solution. Early planning is essential given the significant financial penalties for non-compliance and the potential competitive advantages of proactive renewable energy deployment. Consult specialized legal and technical advisors for site-specific guidance.
[1] However, for public buildings, specific, stricter thresholds apply, as indicated by supplementary information. Although the directly provided legal text (Arts. 6.7.2 - 6.7.5) primarily focuses on the general threshold of over 1 GWh, various external sources consistently highlight the lower thresholds for public buildings. For this category of buildings, the threshold is 250 MWh per year. From 2030, this threshold for public buildings will be further lowered to 100 MWh per year, based on consumption from 2026 onwards. This differentiation in the regulation points to a two-pronged strategy, where the Flemish Government imposes stricter requirements on its own entities or public actors.